Appendix 1: Programme Update

Assisted Collections

 

Project objectives

Redesigning the Assisted Collection service to deliver improvements to residents and crews

Overall RAG status (including explanation)

Previous report

This report

Green

Green

Project start date

January 2022

Project end date

November 2023

 

Reporting period

March to September 2023

Key planned activities

Complete mop-up for kerbside refuse rounds

Complete mailout for communal assisted collections

 

Key achievements since the last update

Completed kerbside recycling rounds

Removed approximately 1300 assisted collections from the data as no longer required (the final figure will be calculated once the project is complete)

Key dependencies

Customer experience

Digital Cityclean

Health & Safety

Key risks and issues

Resources to deliver project

 

 

 

Bin infrastructure and litter reduction

 

Project objectives

Reducing litter and improving the cleanliness of the city

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

June 2021

Project end date

June 2026

 

Reporting period

March to September 2023

Key planned activities

Continue the roll out of on-the-go recycling bins in parks and across the city

Launch consultation for Phase 2 of managing commercial bins on the highway

Continue the audit of street bins, types, conditions and locations in the city

Review locations and types of seafront bins

Launch enforcement measures for residential bins and boxes

 

Key achievements since the last update

Appointed new Project Officer to lead the work

Reviewed action plan to recommence work

Key dependencies

Fleet Replacement

Carbon Neutral Fund

Key risks and issues

Limited resources to carry out projects.

Competing priorities

Budget restrictions

 

 

 

Commercial bins on the highway

 

Project objectives

Creating and implementing a model to manage commercial bins on the highway across Brighton & Hove

Overall RAG status (including explanation)

Previous report

This report

Green

Amber

Project start date

September 2019

Project end date

December 2023

 

Reporting period

March to September 2023

Key planned activities

Continue to provide further advice and guidance

Launch consultation for Phase 2 of managing commercial bins on the highway

 

Key achievements since the last update

Continued to meet with local businesses on individual and group basis to offer further advice and guidance

Continued to reduce the number of commercial bins on the highway across the T-Zone area

Reduced complaints about commercial bins on the highway

Prepared consultation documents for Phase 2 of managing commercial bins on the highway

Key dependencies

Customer experience

Environmental enforcement

Key risks and issues

Capacity of businesses and other stakeholders to follow new model

National Resources & Waste Strategy

 

 

 

Communal bin system

 

Project objectives

Implementing an improved communal bin service for recycling and refuse as appropriate across the city

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

June 2020

Project end date

March 2024

 

Reporting period

March to September 2023

Key planned activities

Trial side loading mixed recycling and glass bins

Draft specification document after agreeing all bin types

Continue resident engagement

Identify bin assembly location

Draft implementation plan and schedule

 

Key achievements since the last update

Carried out initial engagement with resident groups

Prepared Traffic Regulation Orders for each proposed bin bay location

Finalised bin types for refuse and mixed recycling

Key dependencies

Traffic Regulation Orders

Round structures

Procurement

Key risks and issues

Traffic Regulation Orders

Glass bins

Funding

 

 

 

Customer Experience

 

Project objectives

Improving the customer experience and providing a consistent service to everyone who contacts Cityclean

Overall RAG status (including explanation)

Previous report

This report

Green

Green

Project start date

April 2019

Project end date

Ongoing

 

Reporting period

March to September 2023

Key planned activities

Provide training for more ESAs on Contact Management System for Councillor Enquiries to ensure cover when required

Review TROs to address issues of persistent missed collection due to access issues

Continue to develop Standard Operating Procedures to support the above and provide consistent service

Continue to train and develop team

 

Key achievements since the last update

Responded to 95% of City Environmental Management Stage 1 Complaints within 10 days (100% for City Clean)

Responded to 99% of all Stage 1 Complaints within 20 working days

Started Stage 1 Complaints training to another ESA to enhance resources available to provide responses to complaints

Continued to respond to emails within 24 to 48 hours on average (working days)

Key dependencies

Assisted Collections

Digital Cityclean

Graffiti reduction

Increasing material for recycling

Management Framework

Key risks and issues

Loss of support for project

Industrial action

 

 

 

Digital Cityclean

 

Project objectives

Modernising the service and supporting the wider programme of change through technology

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

June 2020

Project end date

February 2025

 

Reporting period

March to September 2023

Key planned activities

Scope further processes in Trade Waste

Continue to document procedures post-implementation for new way of working

Continue to scope weighbridge integration requirements

Populate system with full Trade Waste datasets – rounds, events, attributes and accounts

Organise installation of nine mounting kits

Continue gathering assisted collections information

 

Key achievements since the last update

Started implementation of Phase 1 – Trade Waste

Finalised finance integration with Bartec

Identified nine vehicles for the mounting kit installations

Key dependencies

Assisted Collections

Communal bin system

Customer experience

Key risks and issues

IT&D resources & capacity

Implementation timescales

Existing poor data

Withdrawal of support from workforce or trade unions

 

 

 

Fleet Strategy

 

Project objectives

Delivering of a 10-year strategy and green procurement plan, providing cost and savings projections. The strategy includes the migration to new technology as it develops, such as hydrogen fuel cells, to reduce maintenance and carbon emissions

Overall RAG status (including explanation)

Previous report

This report

Green

Green

Project start date

March 2022

Project end date

March 2030

Reporting period

March to September 2023

Key planned activities

Receive delivery of first electric communal waste truck

Implement new CPC training

Start work on Accident Reduction Policy

Key achievements since the last update

61 electric vehicles in Operation

Four electric HGVs working daily

Seven additional electric HGVs on order

Key dependencies

Communal bin system

Customer experience

Digital Cityclean

Food waste

Health & Safety

Hollingdean Depot

Operator’s Licence

Procurement review

Key risks and issues

Resources – both time and finance

Power infrastructure implemented and available

Competing priorities e.g. service delivery and modernisation and improvement work

Brexit – vehicles purchased from Europe

National Resources & Waste Strategy

Delays with contracts

Support for electric vehicles

 

 

 

Flyering

 

Project objectives

Improving the flyering service by reviewing the flyering framework and extending the current flyering zones

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

March 2022

Project end date

March 2024

Reporting period

March to September 2023

Key planned activities

Print notices

Review consultation responses and take objections to Committee

Implement online payment system

Review and update current webpage

Key achievements since the last update

Notices finalised and published

28-day consultation completed

Finalised terms and conditions

Reviewed application form

Partnered with the Events team on licence requirements

Key dependencies

Environmental Enforcement

Communications

Print & Sign

Key risks and issues

Objections to Notices

Decrease in flyering licences

Resources - staff, and possibly budget

 

 

 

Food waste collections

 

Project objectives

Complete analysis of food waste options

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

June 2021

Project end date

March 2024

 

Reporting period

March to September 2023

Key planned activities

Await further announcements from government on implementation and new burdens funding

Review food waste collections study completed in 2021

Develop costed options for a new food waste collection service

 

Key achievements since the last update

Continued attending DEFRA waste reforms forum to understand requirements of food waste implementation and receive updates

Recruited Project Manager for food waste collections; to start in September 2023

Key dependencies

Communal bin system

Fleet strategy

Customer experience

Procurement review

Key risks and issues

Consistency announcements on other materials 

Data availability

Space availability at the depot, to accommodate the required number of vehicles in accordance with the operators’ licence.

IVC capacity only seasonal, identification of an alternative

Workforce resistance to change

 

 

 

Graffiti Reduction Strategy

 

Project objectives

Delivering the aims of Graffiti Reduction Strategy, reducing the amount of graffiti vandalism around Brighton & Hove

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

November 2018

Project end date

December 2023

 

Reporting period

March to September 2023

Key planned activities

Hold a public consultation and a series of engagement events to refresh Graffiti Tagging Reduction Strategy and Action Pan

 

Key achievements since the last update

Continued community engagement activities, meeting with various LATs and Resident Associations to discuss partnership work

Continued working with Sussex Police and ongoing Joint Action Group

Regular meetings with Sussex Police at the Level Hub intel sharing on prolific taggers

Furthered enforcement action and investigation regarding two prolific taggers

Installed two CCTV cameras at the Level for reduction and prevention of graffiti

Ceased issuing of Community Protection Warning and Notices to small, localised businesses following a decision by Committee

Continued work with Statutory Undertakers for graffiti removal

Removed graffiti on bridge along Dyke Road Drive and wall along Highcroft Villas

Key dependencies

Customer experience

Environmental enforcement

Digital Cityclean

Key risks and issues

Commercial property owners and Statutory Undertakers do not comply with Community Protection Warnings

Challenges to identify and catch taggers

Murals getting tagged and lack of ongoing maintenance

 

 

 

Health & Safety

 

Project objectives

Improving health & safety compliance and performance across City Environmental Management

Overall RAG status (including explanation)

Previous report

This report

Amber

Green

Project start date

January 2021

Project end date

Ongoing

 

Reporting period

March to September 2023

Key planned activities

Complete training matrix for City Parks

Introduce maintenance regime for City Parks work equipment to help manage HAV (Hand Arm Vibration) risk

Update noise action plans

Review City Clean Risk Assessments

Update City Parks Fire Risk Assessments

Provide back of truck safety training at Hollingdean Depot

Undertake further priority audits on a risk basis 

 

Key achievements since the last update

Issued new radios the Public Toilet Team to manage lone working risk

Appointed new City Parks H&S Officer to support further improvements in health and safety performance management 

Delivered City Parks manual handling training for staff

Updated hand-arm-vibration action plans including purchasing accelerometer for measuring equipment vibration levels 

Key dependencies

Assisted Collections

Fleet Strategy

Hollingdean Depot

Management Framework

Operator’s Licence

Workstyles

Key risks and issues

Constantly emerging new priorities and risks e.g. incident investigation, union raised issues

Ongoing need for modernisation of the service including health and safety performance management, with suitable and sufficient risk assessments backed up by a working, evidencable training matrix

Health & Safety Executive interventions and recommendations

Resources to deliver priorities

 

 

 

Increasing material for recycling

 

Project objectives

Completing a feasibility study into the costs of introducing a wider range of materials into the recycling stream at Hollingdean Materials Recovery Facility Preparing for the implementation of the Environment Act

Overall RAG status (including explanation)

Previous report

This report

Green

Amber (due to continuing delays on announcements regarding the Environment Act)

Project start date

January 2022

Project end date

2027

 

Reporting period

March to September 2023

Key planned activities

Continue preparations for the Environment Act and refine plans to be in a position to make a bid to the government for burdens funding

 

Key achievements since the last update

Recruited a Project Manager for food waste collections 

Recruited a Waste Minimisation Officer 

Continued to prepare for the Environment Act reforms in line with the latest information available 

Continued to progress the trial of a new communal bin system in Brunswick & Adelaide and Regency wards, placing refuse, recycling and glass containers at each site to make it easier for residents to dispose of their waste

Continued attending DEFRA LA forum to receive policy updates

Key dependencies

Customer experience

Digital Cityclean

Fleet Strategy

Food waste

Operator’s Licence

Key risks and issues

Outcomes from National Resources & Waste Strategy consultation currently unknown

Resources – both time and finance

 

 

 

 

 

 

Management Framework

 

Project objectives

Improving management processes at Cityclean to ensure BHCC policies and processes are followed

Overall RAG status (including explanation)

Previous report

This report

Amber

Green

Project start date

July 2022

Project end date

Ongoing

 

Reporting period

March to September 2023

Key planned activities

Manage the outcome of the Whistleblowing Report

Continue performance management of crews

Invest management resource on continuing to carefully manage collection of missed work

Complete Annual Performance Review for all front- line operational staff; share and discuss key performance data, as well as delivery against job description with key objectives set

Move Communal Recycling to a 4-on-4-off-rota to improve reliability of collections

Deliver ‘back of vehicle’ refresher training for all Refuse & Recycling manual staff

Review key service plans e.g. Weeds, Public Toilets and Beach

Commence procurement for traffic management to enable twice yearly A27 litter pick

Commence engagement with Trade Unions and staff regarding start and finish at the Depot for 41 hours per week

 

Key achievements since the last update

Agreed key Standard Operating Procedures (SOPs), though progress has been slower than expected due to vacancy for Operations Project Manager

Started to address restrictive work practices at Cityclean by meeting with crews and instructing them to collect their own missed work when there is capacity within their working week to do so

Improved recruitment process e.g. Public Toilets seasonal staff, short film produced, drop in to support office staff with literacy or digital skills. Individual coaching on interview skills provided

Completed Mid-Year Reviews for majority of staff

Key dependencies

Political support

Customer Experience

Hollingdean Depot

Operator’s Licence

Key risks and issues

Unofficial actions such a ‘go slow’ resulting in increased missed work

Withdrawal of support from workforce or trade unions and industrial action

HSE (Health & Safety Executive) interventions and recommendations

National Resources & Waste Strategy

 

 

Operator’s Licence

 

Project objectives

Maintaining the current standing of the BHCC Operator’s Licence

Overall RAG status (including explanation)

Previous report

This report

Green

Green

Project start date

September 2019

Project end date

Ongoing

 

Reporting period

March to September 2023

Key planned activities

Continue with new Brake Testing Equipment

Continue with new Tacho calibration Machine

Create accident reduction programme

Key achievements since the last update

Maintained good standing with Traffic Commissioner

All Fleet records now digital

New contingency site at Hangleton Bottom approved

All drivers recording hours digitally

Key dependencies

Fleet Strategy

Health & Safety

Hollingdean Depot

Management Framework

Key risks and issues

Withdrawal of support from workforce or trade unions

HSE (Health & Safety Executive) interventions and recommendations

National Resources & Waste Strategy

 

 

 

Procurement Review

 

Project objectives

Improving the procurement and contract management in Cityclean to deliver value for money and comply with council policies and procedures

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

June 2022

Project end date

Ongoing

 

Reporting period

March to September 2023

Key planned activities

Begin review of textile recycling contract

Support management and implementation of new integrated waste management software contract

Support communal bin procurement project

Support Fleet with future compliant procurement of spare vehicle parts and maintenance

Support procurement of new fuel supply contact for depot

Further refine and deliver programme of compliance across service

Continue contract management of PPE contract, external recycling providers and toilet consumables suppliers

 

 

Key achievements since the last update

Maintained regular contract management of key external suppliers, including clinical waste, carton recycling, textile recycling, PPE and uniform supply, public toilet consumables (ongoing regular contract meetings)

Assisted delivery of new two-way radio contract

Identified further areas of non-compliance in City Environment (ongoing)

Supported communal bin procurement process (ongoing)

Extended PPE and uniform supply contract by extra year

Maintained Cityclean contract register

Supported City Parks with procurement of equipment and street furniture

Supported delivery of Allotment software project

Supported Fleet with procurement projects (ongoing)

Key dependencies

Communal bin system

Fleet Strategy

Food waste

Key risks and issues

Competing and varying priorities

 

 

 

Public toilets: service options

 

Project objectives

Identifying opportunities and delivering actions to sustain public toilet provision

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

January 2022

Project end date

June 2025

Reporting period

March 2023 to September 2023

Key planned activities

 

 

 

 

Finalise sites for Phase 2 of the Refurbishment Programme

Finalise revised sites for Changing Places locations and seek sign off from DLUHC

Publish tender documents for Phase 2 of the Refurbishment Programme

Publish tender documents for new Changing Places Toilets

Continue to recruit to vacant posts / hours

Continue to manage resources dynamically to provide as much provision as possible

Continue options appraisal work

 

 

 

 

Key achievements since the last update

Appointed a Public Toilet Programme Manager

Reopened the four Phase 1 Refurbishment Programme sites (Daltons, Kings Esplanade, Station Road Portslade, and Saltdean Undercliff)

Reopened Park Road, Rottingdean which was majority-funded by Rottingdean Parish Council

Completed lessons learned for Phase 1 to inform Phase 2

Started scoping Phase 2 Refurbishment Programme sites

Reviewed the locations for the government’s Changing Places funding to be spent as some original locations now not suitable

Completed procurement for the Stanmer Park Changing Places Toilet; work will start on site in September

Continued with recruitment to the Public Toilet Team; not all hours have been filled and so some sites remain on winter hours; staff are being used dynamically to provide as much provision as possible

Started options appraisal work to determine the most viable option to sustain toilet provision; this may include transfer to businesses or communities, whilst remaining as publicly accessible toilets

Reviewed governance arrangements for various Public Toilet projects and created a Public Toilet Programme Board in July 2023 which is being overseen by the Public Toilets Programme Manager

Key dependencies

Customer Experience

Key risks and issues

Staffing levels

Resources – both finance and time

Unbudgeted costs (such as utilities & unexpected maintenance costs) putting public toilets budget at risk of overspend

Supply chain issues

Cost of refurbishment exceeds agreed budget due to cost inflation

Closure of sites for refurbishment may lead to complaints

Refurbishment contractor unable to maintain/recruit sufficient staffing levels

Contractor not delivering on the agreed specification and/or timescales

Unforeseen work issues may exceed agreed budget

 

 

 

Recycling point audit

 

Project objectives

Reviewing existing recycling point locations

Overall RAG status (including explanation)

Previous report

This report

Green

Amber

Project start date

June 2022

Project end date

June 2023

 

Reporting period

March to September 2023

Key planned activities

Explore options for containment and collection method for WEEE

Monitor and measure impact of recently increased capacity for carton recycling at recycling points

Work with Waste Minimisation Officer on raising awareness of fire risk from batteries and disposable vapes

 

Key achievements since the last update

Carton recycling capacity increased at six hotspots across the city

Irreparable Waste Electrical and Electronic Equipment (WEEE) banks removed from four recycling points

Website information and maps for WEEE and carton recycling updated

Key dependencies

Improving the communal bin system

Recycling Quality Assurance report for textile and cartons recycling

Procurement of WEEE bins

Food waste options

Bin Infrastructure

Key risks and issues

Budget restrictions

Bin vandalism and waste theft (WEEE)

Increased fly-tipping

Graffiti and bin tagging

 

 

 

 

 

 

Weed management

 

Project objectives

Implementing sustainable and cost-effective ways of managing weeds without the use of pesticides

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

July 2019

Project end date

March 2023

 

Reporting period

March to September 2023

Key planned activities

Continue to deliver 2023 Weeding Plan

Review and measure impact of the Plan to provide feedback and options for future committee report

Continue to assess alternative methods of weed removal

Deliver proactive Communication plan.

Continue joint working with City Transport

 

Key achievements since the last update

Implemented 2023 Weeding Plan, including traffic light system

Doubled the number of roads cleared of weeds on the previous year

Continued to assess alternative methods of weed removal.

Released communications relating to weeding and new machinery

Key dependencies

Customer experience

Key risks and issues

Competing priorities

Lack of resources if staff leave and there is a lag with recruitment

Musculo Skeletal injuries as staff have increased the time they spend weeding

 

 

Workstyles

 

Project objectives

Creating new office space at Hollingdean Depot, incorporating Workstyles principles

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

November 2019

Project end date

TBC

 

Reporting period

March to September 2023

Key planned activities

Prepare for demolition of old building

Reroute of electrics from old building

Assess current concrete base

Redevelop wash-bay area

Refurbish of depot heating and hot water system

 

Key achievements since the last update

Received permission from Policy & Resources Committee to demolish old offices and replace with new building, and for associated funding

Completed relocation of server room

Installed new ISDN lines

Refurbished canteen

Key dependencies

Health & Safety

Hollingdean Depot

Planning permission

Key risks and issues

Staff working in portacabins which are coming to end of life and do not provide sufficient space, exacerbated since the pandemic

Resources – both time and finance